 Under Construction

FAUMC Multi-Purpose Building

Groundbreaking Ceremony Pictures: April 13th, 2008
Steel Arrives : April 22, 2008 @ 8AM
Grading has begun: May 5, 2008 @ 12PM
 
Starting the Footings: Digging begins May 12, 2008
Concrete for footings is poured: May 13 & 14, 2008
          
Block for foundation: May 15 - 21, 2008
   
Sub-ground, plumbing & gravel: May 26-30
Pouring the Slab: June 2nd
Laying Brick: June 3rd
Preparations for a New Sidewalk: June 9
Installing the Drainage: June 10-13
Retaining Wall & Putting Up Steel: June 18-Present
Topped Out: June 24
Metal Roof & Insulation: July 2nd-July 21st
Block Work & Door Frames: July 22nd - August 6
Sealant: August 8
Begin Brick Veneer & Metal Studs: August 12 & 13
Begin Putting up Board: August 14
A Look inside: September 5
Current View of Exterior: September 5
The View from inside: September 5
Inside View (Insulation & Basketball Goals): September 22

Ready for Sheetrock

Sheetrock & Windows: September 25
Primer & Paint: October
Paint & Stucco: October
Gym Floor (Tile): October 24-
Parking Lot & Mezzanine

Certificate of Occupancy is acquired December 2008